Содержание
- 2. Both SAG and both ball mills are now fully operational. All the basic machinery that supplies
- 3. LEFA Operations - Process (Fayalala, Bofeko, Kankarta) MINING (Lero, Karta, Camp de Base, Pharmacie) CRUSHING MINING
- 4. Crushers at Lero Karta and Fayalala. Overland conveyor (CV4) from Lero Karta to process plant. SAG
- 5. Major Issues resolved Both crushers had the bin support structures reinforced to stop movement, which interfered
- 6. The ROM bin support structures were reinforced to stop movement. Lero & Fayalala Crushers
- 7. Apron feeder chains & pans have been replaced at the Lero crusher, pans and chains will
- 8. Major Issues remaining: Fayalala bin has tendency to block due to design fault. This limits direct
- 9. Major Issues resolved Replacement of the drive gearboxes as design faults were limiting the performance. The
- 10. CV4 Overland Conveyor Covers over belt.
- 11. Major Issues remaining The only remaining concern is the construction of the conveyor system which can
- 12. CV4 Overland Conveyor CV04 clip repair
- 13. Major Issues resolved In June 2009 extensive damage to the bearing mating surface on the Discharge
- 14. SAG Mill General Arrangement
- 15. Two spare gearboxes (left and right) are on site. Scheduled to be installed on SAG 1
- 16. Major Issues remaining New trunnions from REMAS in Turkey have been completed and ready for shipping.
- 17. Casting/forging of the SAG mill trunnions is completed in Turkey. SAG Mill 1
- 18. Oil Centrifuge Trunnion Lube Pack LUBEMASTER Centrifuges have been installed on to both SAG Mill lube
- 19. Major Issues resolved The discharge end trunnion for this mill was removed for machining by REMAS
- 20. The trunnion for this mill was removed for machining by REMAS in Turkey and returned in
- 21. SAG Mill 2 SAG Mill 2, Trunnion being repaired by REMAS in Turkey. After machining, sub-arc
- 22. SAG Mill 2 SAG Mill 2, Trunnion being repaired by REMAS in Turkey Machining back to
- 23. Major Issues remaining The trunnion that was repaired by REMAS in Turkey still has a problem
- 24. Premature SAG Mill Trunnion Bearing failures remain a concern until new trunnion seals and accumulator for
- 25. 400 kg SAG Mill 2 SAG Mill 2 bearings were hand scraped for the best possible
- 26. SAG Mill 2 New Bearing Pads after installation showing excellent oil coverage.
- 27. Bearing Pad Thrust Bearing Trunnion Thrust face Trunnion Journal surface SAG Mill 2
- 28. Major Issues resolved The electric drive motor was recently completely overhauled and is expected to provide
- 29. The electric drive motor was recently completely overhauled and is expected to provide a fully serviceable
- 30. Ball Mill 1 Ball Mill 1 motor being lifted away from the Mill. Motor weighs 28T
- 31. Ball Mill 1 Motor being loaded onto an Antonov Aircraft bound for Antwerp for overhaul. Ball
- 32. Ball Mill 2 New Ball Mill being loaded onto Truck for transporting to site.
- 33. Major Issues remaining A trommel needs to be sourced and installed. The current internal screen to
- 34. Major Issues resolved The motor on Ball Mill 2 went down in late August on High
- 35. The motor on Ball Mill 2 went down in late August on high temperature on the
- 36. Ball Mill 2 Failed set of white metal bearings. A new set of bearings were installed
- 37. Major Issues remaining: A Trommel needs to be sourced and installed. The current internal screen to
- 38. Ball Mill 2 was breaking feed end flange bolts. The end plate mating surfaces and trunnion
- 39. Major Issues resolved: The cyclones installed were obsolete and it had been difficult to maintain a
- 40. New cyclones cluster being installed in August 2009. Cyclones
- 41. Cyclones New cyclones cluster being installed in August 2009. New Cyclone Underflow pan before being lifted
- 42. Major Issues remaining: The design and condition of the current cyclone feed pipe is poor and
- 43. Major Issues resolved: New thermal heaters, to resolve the downtime associated with the derelict glycol boilers
- 44. Elution, electrowinning and smelting. New thermal heaters, associated pump packs, heat exchangers and prefabricated pipe work,
- 45. Major Issues resolved: New cyanide mixing and holding tanks have been constructed. The caustic mixing tank,
- 46. Reagent Mixing New Cyanide mixing and storage tanks
- 47. Reagent Mixing New Caustic tank with Hopper structure being assembled.
- 48. Major Issues resolved: Total capacity of eight 4.5 MW units, equivalent to 36 MW installed. Normal
- 49. Power generating plant
- 50. Fabrication training is leading the way with dedicated Trainers. A training matrix has been developed and
- 52. Скачать презентацию