LEFA Operations

Содержание

Слайд 2

Both SAG and both ball mills are now fully operational.
All the basic

Both SAG and both ball mills are now fully operational. All the
machinery that supplies ore to the mills or pulp coming from the mills is running, although reliability remains below optimum.
The de-bottlenecking projects will continue to ensure that reliability of all machinery is at acceptable levels.
It is expected that maintenance will normalise in early 2010 and throughput appears to confirm this.
There remains some minor risk of interruption to production well into 2010, until all of the ordered insurance spares are on site.

Overview of Current Status

Слайд 3

LEFA Operations - Process

(Fayalala, Bofeko, Kankarta)

MINING

(Lero, Karta, Camp de Base, Pharmacie)

CRUSHING

MINING

LEFA Operations - Process (Fayalala, Bofeko, Kankarta) MINING (Lero, Karta, Camp de

MILLING

CLASSIFICATION

THICKENER

ELUTION & ELECTROWINNING

CIP CIRCUIT

Fayalala ROM Pad

Lero ROM Pad

Emergency stockpile

SMELTING

GOLD 99.99%

Bullion

TAILING & WATER RECYCLE

WATER POND

Слайд 4

Crushers at Lero Karta and Fayalala.
Overland conveyor (CV4) from Lero Karta to

Crushers at Lero Karta and Fayalala. Overland conveyor (CV4) from Lero Karta
process plant.
SAG mill 1 and SAG mill 2.
Cyclone feed pumps and cyclones.
Ball mill 1 and ball mill 2.
Thickeners.
Gold leaching and carbon adsorption circuit.
Elution, electrowinning and smelting.
Tailings disposal

Major Components of Process

Слайд 5

Major Issues resolved
Both crushers had the bin support structures reinforced to stop

Major Issues resolved Both crushers had the bin support structures reinforced to
movement, which interfered with the apron feeder operation causing through-put interruptions. The work was substantially more at Fayalala.
Apron feeder major components have been replaced at the Lero crusher.
Vibrating grizzly replaced at Lero

Lero & Fayalala Crushers

Слайд 6

The ROM bin support structures were reinforced to stop movement.

Lero & Fayalala

The ROM bin support structures were reinforced to stop movement. Lero & Fayalala Crushers
Crushers

Слайд 7

Apron feeder chains & pans have been replaced at the Lero crusher,

Apron feeder chains & pans have been replaced at the Lero crusher,
pans and chains will be replaced in 2010 at the Fayalala crusher.

Lero & Fayalala Crushers

Слайд 8

Major Issues remaining:
Fayalala bin has tendency to block due to design fault.

Major Issues remaining: Fayalala bin has tendency to block due to design
This limits direct tipping. This is scheduled to be resolved in the course of the year.
Pans and chains on the Fayalala apron feeder and a new vibrating grizzly is scheduled in October 2010. The current unit is under a strict condition monitoring program to mitigate any propagating maintenance issues. Chains and half the pans on the Fayalala apron feeder were previously replaced in January 2008. The replacement of the pans is now required and the chains are also being replaced to reduce the overall downtime to the crusher for this job. The chains that are removed will be kept as spares for the future.

Lero & Fayalala Crushers

Слайд 9

Major Issues resolved
Replacement of the drive gearboxes as design faults were limiting

Major Issues resolved Replacement of the drive gearboxes as design faults were
the performance. The gearboxes were modified to solve lubrication problems associated with bearings. Original gearbox assemblies shall be overhauled in-house and maintained as Insurance Spares.
Damaged belt renewed.
Modification to feed chute to reduce jams and damage to belt.
Cover of belt to reduce saturation of the ore during the wet session.
Installation of belt tracking frames to reduce belt damage.

CV4 Overland Conveyor

Слайд 10

CV4 Overland Conveyor

Covers over belt.

CV4 Overland Conveyor Covers over belt.

Слайд 11

Major Issues remaining
The only remaining concern is the construction of the conveyor

Major Issues remaining The only remaining concern is the construction of the
system which can be described as cheaply built, with little clearance between carry and return belt support structure. This remains a threat as rock spillage from feed belt onto the returning belt can be trapped within the support frames, resulting in belt damage. However there are no plans to replace this structure due to cost constraints.
April 2010 a major rip in CV04 of 3572 metres occurred, 1300 metres has been replaced with belt that was in stock, the remaining 2272 metres of damaged belt was clipped at 500mm intervals and also had a Bandage strip glued to the underside to reduce spillage, this bandage strip will be inspected weekly and replaced as required
Replacement belt is being sourced and expedited to site to replace the remaining damaged section of belt.

CV4 Overland Conveyor

Слайд 12

CV4 Overland Conveyor

CV04 clip repair

CV4 Overland Conveyor CV04 clip repair

Слайд 13

Major Issues resolved
In June 2009 extensive damage to the bearing mating surface

Major Issues resolved In June 2009 extensive damage to the bearing mating
on the Discharge End trunnion was discovered. This damage was similar, but less severe, to that of SAG 2.
Grinding and polishing of the trunnion in situ by external contractors, (“Hoffmans”), was initiated to a provide a temporary repair and SAG Mill 1 was reinstated into full operation in early September providing the site with two operating SAG mills.
The repair is expected to allow the mill to operate until the replacement of the trunnions in fourth quarter of 2010.
Two spare SAG mill gearboxes (left and right) are on site and will be installed on SAG 1 in 2010, as the current unit’s service life is unknown. The units removed will be overhauled and changed out on SAG 2. At the completion of this program the two overhauled spare gearboxes from SAG 2 will be held as insurance spares.
A spare SAG mill motor is on site as an Insurance Spare. A second will be ordered, cash flow permitting in 2010. Electric motors of this size have a considerable long lead time for delivery which can exceed 52 weeks.

SAG Mill 1

Слайд 14

SAG Mill General Arrangement

SAG Mill General Arrangement

Слайд 15

Two spare gearboxes (left and right) are on site.
Scheduled to be installed

Two spare gearboxes (left and right) are on site. Scheduled to be
on SAG 1 in July / August 2010.

SAG Mill 1

Слайд 16

Major Issues remaining
New trunnions from REMAS in Turkey have been completed and

Major Issues remaining New trunnions from REMAS in Turkey have been completed
ready for shipping. The completed trunnions are expected to be installed in the planned October shutdown. The existing Discharge trunnion will be scrapped due to cracks in journal surface, the Feed end Trunnion will be repaired for Insurance spare.
SAG Mill discharge end trunnion bearings need to be replaced every 6 to 8 months due to excessive wear (normally last plus 10 years). The main reason for damage is thought to be loss of pressure to the oil separating the trunnion from the bearing during power outages and contamination of the oil due to poor design of the trunnion seals. A re-engineered seal and an accumulators will resolve these issues in 2010. In the meantime, a centrifuge is used to clean the trunnion bearing oil.
The current girth gear and drive train is under a strict condition monitoring program to mitigate any propagating maintenance issues. Site management are currently working with major suppliers for replacement girth gear and pinion as these items have a long lead time, which is likely to be in excess of 55 weeks.

SAG Mill 1

Слайд 17

Casting/forging of the SAG mill trunnions is completed in Turkey.


SAG Mill

Casting/forging of the SAG mill trunnions is completed in Turkey. SAG Mill 1
1

Слайд 18

Oil Centrifuge

Trunnion Lube Pack

LUBEMASTER Centrifuges have been installed on to both SAG

Oil Centrifuge Trunnion Lube Pack LUBEMASTER Centrifuges have been installed on to
Mill lube packs to assist in keeping the oil cleaner until a solution to the Trunnion sealing is sourced.

SAG Mill 1

Слайд 19

Major Issues resolved
The discharge end trunnion for this mill was removed for

Major Issues resolved The discharge end trunnion for this mill was removed
machining by REMAS in Turkey and returned in May 2009.
Two spare SAG mill gearboxes (left and right) are on site and will be installed on SAG 1 in 2010, as the current unit’s service life is unknown. The units removed will be overhauled and changed out on SAG 2. At the completion of this program the two overhauled spare gearboxes from SAG 2 will be held as insurance spares.
A spare SAG mill motor is on site as an Insurance Spare. A second will be ordered, cash flow permitting in 2010. Electric motors of this size have a considerable long lead time for delivery which can exceed 52 weeks.

SAG Mill 2

Слайд 20

The trunnion for this mill was removed for machining by REMAS in

The trunnion for this mill was removed for machining by REMAS in
Turkey and returned in May 2009.

21,000 kg

SAG Mill 2

Слайд 21

SAG Mill 2

SAG Mill 2, Trunnion being repaired by REMAS in Turkey.

SAG Mill 2 SAG Mill 2, Trunnion being repaired by REMAS in
After machining, sub-arc welding to rebuild the surface.

Слайд 22

SAG Mill 2

SAG Mill 2, Trunnion being repaired by REMAS in Turkey
Machining

SAG Mill 2 SAG Mill 2, Trunnion being repaired by REMAS in
back to OEM dimensions.

Слайд 23

Major Issues remaining
The trunnion that was repaired by REMAS in Turkey still

Major Issues remaining The trunnion that was repaired by REMAS in Turkey
has a problem with the Thrust face which is causing elevated temperatures, we are working with REMAS for a solution.
SAG Mill discharge end trunnion bearings need to be replaced every 6 to 8 months due to excessive wear (normally last plus 10 years). The main reason for damage is thought to be loss of pressure to the oil separating the trunnion from the bearing during power outages and contamination of the oil due to poor design of the trunnion seals. A re-engineered seal and an accumulators will resolve these issues in 2010.
In the medium term this Mill will require new pinion cartridges, a new girth gear and the head plate removed and cleaned. Major components for this project are available on site. The current girth gear and drive train is under a strict condition monitoring program to mitigate any propagating maintenance issues. Girth gear and pinions have a long lead time in excess of 55 weeks.

SAG Mill 2

Слайд 24

Premature SAG Mill Trunnion Bearing failures remain a concern until new trunnion

Premature SAG Mill Trunnion Bearing failures remain a concern until new trunnion
seals and accumulator for lubricating oil installed. November 2009 SAG Mill 2 Discharge End.

High wear of Trunnion Bearing Pads

SAG Mill 2

Слайд 25

400 kg

SAG Mill 2

SAG Mill 2 bearings were hand scraped for the

400 kg SAG Mill 2 SAG Mill 2 bearings were hand scraped
best possible contact with the trunnion Journal surface.

Слайд 26

SAG Mill 2

New Bearing Pads after installation showing excellent oil coverage.

SAG Mill 2 New Bearing Pads after installation showing excellent oil coverage.

Слайд 27

Bearing Pad

Thrust Bearing

Trunnion Thrust face

Trunnion Journal surface

SAG Mill 2

Bearing Pad Thrust Bearing Trunnion Thrust face Trunnion Journal surface SAG Mill 2

Слайд 28

Major Issues resolved
The electric drive motor was recently completely overhauled and is

Major Issues resolved The electric drive motor was recently completely overhauled and
expected to provide a fully serviceable life.
A new motor manufactured by ABB in South Africa and is on site as an Insurance Spare that is scheduled for installation into Ball Mill 2 and the existing motor will undergo refurbishment and returned as an Insurance Spare.

Ball Mill 1

Слайд 29

The electric drive motor was recently completely overhauled and is expected to

The electric drive motor was recently completely overhauled and is expected to
provide a fully serviceable life.

Damaged Shaft

Failed White Metal Bearing

Ball Mill 1

Слайд 30

Ball Mill 1

Ball Mill 1 motor being lifted away from the

Ball Mill 1 Ball Mill 1 motor being lifted away from the Mill. Motor weighs 28T
Mill.
Motor weighs 28T

Слайд 31

Ball Mill 1 Motor being loaded onto an Antonov Aircraft bound for

Ball Mill 1 Motor being loaded onto an Antonov Aircraft bound for
Antwerp for overhaul.

Ball Mill

Слайд 32

Ball Mill 2

New Ball Mill being loaded onto Truck for transporting to

Ball Mill 2 New Ball Mill being loaded onto Truck for transporting to site.
site.

Слайд 33

Major Issues remaining
A trommel needs to be sourced and installed. The current

Major Issues remaining A trommel needs to be sourced and installed. The
internal screen to contain balls gets clogged when 2 SAG Mills feed into it. By having a properly designed trommel it will allow more flexibility in operating the mills. This is currently under investigation, and an engineering solution is being sourced.
There are no spare pinions or girth gears for these mills. Site management have now raised AFE for for replacement girth gear and will be manufactured by Hofmann Engineering. A pinion gear for the ball mill is presently being manufactured by Hofmann Engineering, scheduled for delivery in July.
The current girth gear and drive train is under a strict condition monitoring program to mitigate any propagating maintenance issues. Girth gear and pinions have a long lead time in excess of 55 weeks.
Critical and insurance spares have been ordered for both mills, including a spare gear box.

Ball Mill 1

Слайд 34

Major Issues resolved
The motor on Ball Mill 2 went down in late

Major Issues resolved The motor on Ball Mill 2 went down in
August on High Temperature on the non drive end. The shaft was inspected and deemed OK and with no evidence of problems with the windings. A new set of bearings were installed and operating conditions monitored with no indications impending issues.
As this is the second incident where the motor has drifted off magnetic dead centre and caused damage, the replacement of this motor would be recommended in July / August 2010 on a scheduled plant shutdown.
A new motor manufactured by ABB is on site as an Insurance Spare that is scheduled for installation into Ball Mill 2 and the existing motor will undergo refurbishment and returned as an Insurance Spare.

Ball Mill 2

Слайд 35

The motor on Ball Mill 2 went down in late August on

The motor on Ball Mill 2 went down in late August on
high temperature on the non drive end. The shaft was inspected and deemed OK and with no evidence of problems with the windings.

Ball Mill 2

Слайд 36

Ball Mill 2

Failed set of white metal bearings. A new set of

Ball Mill 2 Failed set of white metal bearings. A new set
bearings were installed and operating conditions monitored with no indications impending issues.

Слайд 37

Major Issues remaining:
A Trommel needs to be sourced and installed. The current

Major Issues remaining: A Trommel needs to be sourced and installed. The
internal screen to contain balls gets clogged when 2 SAG Mills feed into it. By having a properly designed trommel it will allow more flexibility in operating the mills. This is currently under investigation, and an engineering solution is being sourced.
There are no spare pinions or girth gears for these mills. Site management are currently negotiating with major suppliers for replacement girth gears and pinions, as these items have a long lead time, in excess of 55 weeks.
Ball Mill 2 keeps breaking feed end flange bolts. This requires the mill to be shut down for a couple of days every two months. The end plate mating surfaces and trunnion require re-machining to reduce stress on the bolts. This was done in May 2010 by Hofmann Engineering with good results.
Critical and insurance spares have been ordered for both mills. A new inching drive has been installed and a spare gear box is being manufactured by Hofmann Engineering.

Ball Mill 2

Слайд 38

Ball Mill 2 was breaking feed end flange bolts. The end plate

Ball Mill 2 was breaking feed end flange bolts. The end plate
mating surfaces and trunnion have been re-machined to reduce stress on the bolts.

Ball Mill 2

Слайд 39

Major Issues resolved:
The cyclones installed were obsolete and it had been difficult

Major Issues resolved: The cyclones installed were obsolete and it had been
to maintain a stock of spare parts. New cyclones and new distributor and upgraded underflow pans have been installed in August 2009 for cyclone pack 1.
A new second distributor and underpan was installed in February 2010 on cyclone pack 2. The Cyclones in this pack will be replaced by new generation Cyclones as they become available.

Cyclones

Слайд 40

New cyclones cluster being installed in August 2009.

Cyclones

New cyclones cluster being installed in August 2009. Cyclones

Слайд 41

Cyclones

New cyclones cluster being installed in August 2009. New Cyclone Underflow pan

Cyclones New cyclones cluster being installed in August 2009. New Cyclone Underflow
before being lifted into position.

Слайд 42

Major Issues remaining:
The design and condition of the current cyclone feed pipe

Major Issues remaining: The design and condition of the current cyclone feed
is poor and is considered at a considerable risk of failure. New pipe work has been scheduled for installation in late 2010 which will eliminate the design issues.

Cyclones

Слайд 43

Major Issues resolved:
New thermal heaters, to resolve the downtime associated with the

Major Issues resolved: New thermal heaters, to resolve the downtime associated with
derelict glycol boilers have been installed.
A second carbon regeneration kiln was recently delivered to site, which will be installed alongside the existing kiln.
Two new electrowinning cells with increased capacity are scheduled to be installed in early 2010.
A new gold room vault is under construction.

Elution, electrowinning and smelting.

Слайд 44

Elution, electrowinning and smelting.

New thermal heaters, associated pump packs, heat exchangers and

Elution, electrowinning and smelting. New thermal heaters, associated pump packs, heat exchangers
prefabricated pipe work, to replace the Glycol boilers.

Слайд 45

Major Issues resolved:
New cyanide mixing and holding tanks have been constructed.
The

Major Issues resolved: New cyanide mixing and holding tanks have been constructed.
caustic mixing tank, foundation and bunded walls is complete installation is in progress. The original infrastructure was designed for delivery of liquid caustic, however only solid caustic is available in country.
The acid loading area was poorly designed which creates a safety, environmental and operational hazard. New facilities are complete.

Reagent Mixing

Слайд 46

Reagent Mixing

New Cyanide mixing and storage tanks

Reagent Mixing New Cyanide mixing and storage tanks

Слайд 47

Reagent Mixing

New Caustic tank with Hopper structure being assembled.

Reagent Mixing New Caustic tank with Hopper structure being assembled.

Слайд 48

Major Issues resolved:
Total capacity of eight 4.5 MW units, equivalent to 36

Major Issues resolved: Total capacity of eight 4.5 MW units, equivalent to
MW installed. Normal power draw is close to 20 Mw. Conversion to HFO reduced this capacity to 3.6 MW per unit or installed capacity of 29 MW.
We operate between 80% and 90% on HFO, and 10% to 20% with LFO to periodically flush fuelling nozzles, which block with bitumen after prolonged use of HFO.
The HFO storage capacity of 8 million litres provides an additional buffer against possible disruption to supply in the wet season.
Major Issues remaining:
Fire suppression for the power generation systems has been ordered with an expected cost of in excess of $600,000 USD including installation. As a stop gap measure, 24/7 fire watch is in place, with the emergency response team based at the powerhouse. This remains a vulnerable area for the site, and is classified as a high risk.
Automatic voltage regulators will be installed by April 2010 improving the reliability of the powerhouse and engine load sharing.

Power generating plant

Слайд 49

Power generating plant

Power generating plant

Слайд 50

Fabrication training is leading the way with dedicated Trainers. A training matrix has

Fabrication training is leading the way with dedicated Trainers. A training matrix
been developed and will be utilised site wide.

Training of Guinea Nationals

Имя файла: LEFA-Operations.pptx
Количество просмотров: 131
Количество скачиваний: 0