MS Project Example

Содержание

Слайд 2

New Project Screen

On starting Project a blank template will appear.

LSU 07/26/2004

MS Project

New Project Screen On starting Project a blank template will appear. LSU 07/26/2004 MS Project Example
Example

Слайд 3

Basic Project Information

From the “Project” menu select “Project Information” and enter the

Basic Project Information From the “Project” menu select “Project Information” and enter
anticipated project start date.

LSU 07/26/2004

MS Project Example

Слайд 4

Enter the major tasks

Type in the major tasks (WBS level 1) in

Enter the major tasks Type in the major tasks (WBS level 1)
the “Task Name” box.
Each row is a separate task
Do not worry about the rest of the columns for now

LSU 07/26/2004

MS Project Example

Слайд 5

Insert Rows

Select the row above which you want to insert a subunit
Select

Insert Rows Select the row above which you want to insert a
“New Task” from the “Insert” menu
To delete a row, select the row and press the “Delete” key

LSU 07/26/2004

MS Project Example

Слайд 6

Enter the subunit task names

Type in the name of the subunit task

Enter the subunit task names Type in the name of the subunit
in the “Task Name” field
Subunits are “indented” with the right arrow on the task bar
When subunits are so “indented” the major unit will become bold and the Gantt chart bar will change shape

LSU 07/26/2004

MS Project Example

Слайд 7

Complete entering WBS

Process of inserting rows, typing in the task name and

Complete entering WBS Process of inserting rows, typing in the task name
indenting the subunit continues until all tasks in the WBS are entered

LSU 07/26/2004

MS Project Example

Слайд 8

Display the WBS code

Select the “Information” column, right click and choose “Hide

Display the WBS code Select the “Information” column, right click and choose
Column”.
Next select the “Task Name” column and from the “Insert” menu select “Column”. The following pop-up will appear.
Choose “WBS” as the “Field name”

LSU 07/26/2004

MS Project Example

Слайд 9

Showing the WBS code

The correct WBS code number will now be displayed

Showing the WBS code The correct WBS code number will now be
for all tasks

LSU 07/26/2004

MS Project Example

Слайд 10

Task bars

With all subunits inserted the lowest level will be blue rectangles

Task bars With all subunits inserted the lowest level will be blue
and higher levels will be black bars with points on the ends.

LSU 07/26/2004

MS Project Example

Слайд 11

Distinguishing different levels

You can change the color of the task bar to

Distinguishing different levels You can change the color of the task bar
distinguish between the different levels in your WBS
Select the task bar to change (in the Gantt chart area), right click and select “Format Bar”.
Change the color of the “Start”, “Middle” and “End”

LSU 07/26/2004

MS Project Example

Слайд 12

Results after task bar change

The results of changing the task bar color

Results after task bar change The results of changing the task bar
are shown below

LSU 07/26/2004

MS Project Example

Слайд 13

Set the task durations

Now enter the time associated with each task in

Set the task durations Now enter the time associated with each task
the “Duration” field. See the MS Project Help for choices on units.
Set durations for the lowest level tasks and the total time will be summarized or rolled-up to the next highest level.

LSU 07/26/2004

MS Project Example

Слайд 14

Set the task predecessors

Enter the task dependence (i.e. which tasks must be

Set the task predecessors Enter the task dependence (i.e. which tasks must
complete prior to starting the next task) in the “Predecessors” field.
You need to use the row number, not the WBS code.

LSU 07/26/2004

MS Project Example

Слайд 15

Enter all predecessors

Here all the task predecessors are determined and entered, but

Enter all predecessors Here all the task predecessors are determined and entered,
the Gantt chart now needs room to display fully

LSU 07/26/2004

MS Project Example

Слайд 16

Set the timescale of the chart

From the “Format” menu select “Timescale”
Set the

Set the timescale of the chart From the “Format” menu select “Timescale”
Major Scale to Months
Set the Minor Scale to Weeks

LSU 07/26/2004

MS Project Example

Слайд 17

After timescale change

Now the full Gantt chart from project start to end

After timescale change Now the full Gantt chart from project start to
can be displayed

LSU 07/26/2004

MS Project Example

Слайд 18

Make an image for documents

To make a GIF image that can be

Make an image for documents To make a GIF image that can
inserted into documents, first arrange the chart and task info boundaries to display just what you want.
From the “Edit” menu select “Copy Picture”
Select “To GIF image file:” and enter a filename for the image

LSU 07/26/2004

MS Project Example

Select what to copy: Rows on screen or Selected Rows
Select the timescale as either what is shown on the screen or for specific dates
Click OK and the image will be generated.

Имя файла: MS-Project-Example-.pptx
Количество просмотров: 174
Количество скачиваний: 1