PMC Weekly Progress

Содержание

Слайд 2

CONTENTS

Key Milestones Dates
Progress Analysis
General PMC Management
HSE Management
Engineering
QC Inspections
Construction
Status of P1 Equipment vs

CONTENTS Key Milestones Dates Progress Analysis General PMC Management HSE Management Engineering
Foundation Readiness
Areas of concern
Site photos

PMC SERVICES FOR BGPP

Слайд 3

PMC SERVICES FOR BGPP

KEY MILESTONE DATES

EPC Contractor set dates as shown are

PMC SERVICES FOR BGPP KEY MILESTONE DATES EPC Contractor set dates as
based on Report of 28/06/22. Published deterministic Schedule is expected by 15/08

Слайд 4

PMC SERVICES FOR BGPP

KEY MILESTONE DATES

EPC Contractor set dates as shown are

PMC SERVICES FOR BGPP KEY MILESTONE DATES EPC Contractor set dates as
based on Report of 28/06/22. Published deterministic Schedule is expected by 15/08

Слайд 5

PMC SERVICES FOR BGPP
PROGRESS ANALYSIS

………

PMC SERVICES FOR BGPP PROGRESS ANALYSIS ………

Слайд 6

ENGINEERING TEAM MOBILISATION STATUS

Recruitment Status:
Senior Process Engineer - Open Arts will join

ENGINEERING TEAM MOBILISATION STATUS Recruitment Status: Senior Process Engineer - Open Arts
on 05/09
1 position GGS Senior Process Engineer was removed from HOLD by the Client on 18/08 and is searching by HR

PMC SERVICES FOR BGPP
GENERAL PMC MANAGEMENT

PROJECT MANAGEMENT TEAM STATUS

Слайд 7

PMC SERVICES FOR BGPP
GENERAL PMC MANAGEMENT

PMC CONSTRUCTION TEAM MOBILISATION STATUS

Recruitment Status
3

PMC SERVICES FOR BGPP GENERAL PMC MANAGEMENT PMC CONSTRUCTION TEAM MOBILISATION STATUS
positions on site were requested to be fulfilled by Client on 26/07 with effect by 1st week of September. HR is searching for:
Inspector - Mechanic of technological equipment
Inspector of welding works
Inspector of electrical assembly works
B2B for Head of the technical supervision group on logistics and goods acceptance and receipt inspection - Tursyn Akhmetov will join on 11/09

Слайд 8

REPORTED WEEK 85/130

No new COVID-19 cases registered in PMC team last week.
PMC

REPORTED WEEK 85/130 No new COVID-19 cases registered in PMC team last
HSE Recommendation for a period:
To keep maintain of the first stage of control logbook, as there are no records on correction of previously issued observations. Conduct an unscheduled briefing with the person in charge.
To arrange temporary storage of the metal structure with pallets and pads
To install a medical station wagon with all the necessary medical equipment (stretchers, splints, refrigerator, medical room, etc.) and medicines on the territory of the GPP, with the organization of round-the-clock duty by medical personnel
Unsafe scaffolding is observed on area Area 460-00-ТМ-71, 72А. To install the boards flat, widen the planking, install the boarding elements on the working deck of the scaffolding.
To ensure staff is smoking in specialized smoking area of the pipe shop

MONITORING COVID-19 SITUATION IN UZBEKISTAN

PMC SERVICES FOR BGPP
HSE MANAGEMENT

Open for the week: 35

Слайд 9


PMC SERVICES FOR BGPP
GENERAL PMC MANAGEMENT

CLOSED CORRESPONDENCE / ACTIONS /

PMC SERVICES FOR BGPP GENERAL PMC MANAGEMENT CLOSED CORRESPONDENCE / ACTIONS /
DECISIONS / APPROVALS

OPEN CORRESPONDENCE / ACTIONS / DECISIONS / APPROVALS

SIGNIFICANT CORRESPONDENCE

Слайд 10

PMC SERVICES FOR GPP
GENERAL PMC MANAGEMENT


REPORTED WEEK 85/130

UPCOMING WEEK 86/131

PMC SERVICES FOR GPP GENERAL PMC MANAGEMENT REPORTED WEEK 85/130 UPCOMING WEEK 86/131

Слайд 11

PMC SERVICES FOR BGPP
ENGINEERING – HIGHLIGHTS

SIGNIFICANT TRANSMITTALS

PMC SERVICES FOR BGPP ENGINEERING – HIGHLIGHTS SIGNIFICANT TRANSMITTALS

Слайд 12

PMC SERVICES FOR BGPP
ENGINEERING – CRITICAL ISSUES

PMC SERVICES FOR BGPP ENGINEERING – CRITICAL ISSUES

Слайд 13

PMC SERVICES FOR BGPP
ENGINEERING – CRITICAL ISSUES

PMC SERVICES FOR BGPP ENGINEERING – CRITICAL ISSUES

Слайд 14

PMC SERVICES FOR BGPP
ENGINEERING – CRITICAL ISSUES

PMC SERVICES FOR BGPP ENGINEERING – CRITICAL ISSUES

Слайд 15

Not issued

Reported forecast dates to issue AFU of some of Open philosophies/Studies

Not issued Reported forecast dates to issue AFU of some of Open
are slipped

PMC SERVICES FOR BGPP
TECHNICAL SAFETY ENGINEERING: PHILOSOPHIES AND STUDIES STATUS

Слайд 16

PMC SERVICES FOR BGPP
TECHNICAL SAFETY ENGINEERING: PHILOSOPHIES AND STUDIES STATUS

PMC SERVICES FOR BGPP TECHNICAL SAFETY ENGINEERING: PHILOSOPHIES AND STUDIES STATUS

Слайд 17

PMC SERVICES FOR BGPP
TECHNICAL SAFETY ENGINEERING: PHILOSOPHIES AND STUDIES STATUS

PMC SERVICES FOR BGPP TECHNICAL SAFETY ENGINEERING: PHILOSOPHIES AND STUDIES STATUS

Слайд 18

PMC SERVICES FOR BGPP
ELECTRICAL ENGINEERING: STUDIES STATUS

PMC SERVICES FOR BGPP ELECTRICAL ENGINEERING: STUDIES STATUS

Слайд 19

PMC SERVICES FOR BGPP
ELECTRICAL ENGINEERING: STUDIES STATUS

PMC SERVICES FOR BGPP ELECTRICAL ENGINEERING: STUDIES STATUS

Слайд 20

Compare with the previous week the progress increased by 2.14% as Planned

Compare with the previous week the progress increased by 2.14% as Planned
progress has been changed from 62,56% to 60,99%
The overall quantity of deliverables in MDR for a week period is increased by 36.
Total foreseen deliverables till now are 9 687 deliverables

PMC SERVICES FOR BGPP
ENGINEERING - GPP MDR ANALYSIS

Слайд 21

REPORTED WEEK 84/129

UPCOMING WEEK 85/130

PMC SERVICES FOR BGPP
QC INSPECTIONS

Reports forwarded with

REPORTED WEEK 84/129 UPCOMING WEEK 85/130 PMC SERVICES FOR BGPP QC INSPECTIONS
official transmittals
Review and commenting of Inspection Status Report
Contract arrangement with RINA EMEA B.V. and ACE Plantech CO., Ltd is in process by PMC

PMC receives Inspection Procedures in some cases with errors, not approved or drawings are missing. For instance:
Hydrotest Procedure indicated a test pressure different from that indicated in the drawing. Ref: NFI-BOGPZ-21294-SE-004-R0
Vendor was unable to provide drawing during testing. Ref: NFI-BOGPZ-20.188-FTMS-025-R0
EPC Contractor should send all the latest revision of approved documents relevant to the inspection along with the NFI in order to negate any inspection being done with a wrong parameter and thus avoid the need to re-test or re-inspect.

Слайд 22

REPORTED WEEK 85/130

Supervision / Inspection of ongoing works;
Monitor HSE aspects during

REPORTED WEEK 85/130 Supervision / Inspection of ongoing works; Monitor HSE aspects
the execution of construction work;
Issue of daily progress reporting;
Incoming control inspection of construction materials arriving at the site;
Checking of the quality of executive act documentation for the compliance with EPC Contract and the local regulatory requirements;
Participation in the technical supervision, construction progress and quality control coordination meetings with the contractor.

UPCOMING WEEK 86/131

REPORTED WEEK 85/130

25 missed AFC Detailed Design
18 not complying with the Detailed Design, exceeding the standards tolerances
5 uncompleted incoming control of materials

Issued for the week:42

PMC SERVICES FOR BGPP
CONSTRUCTION- HIGHLIGHTS

Rejected for the week: 5

Слайд 23

PMC SERVICES FOR BGPP
CONSTRUCTION- NCR STATUS

PMC highlights, ……………..

PMC SERVICES FOR BGPP CONSTRUCTION- NCR STATUS PMC highlights, ……………..

Слайд 24

PMC SERVICES FOR BGPP
STATUS OF P1 EQUIPMENT VS FOUNDATION READINESS

265-00-PK-02 awaiting for

PMC SERVICES FOR BGPP STATUS OF P1 EQUIPMENT VS FOUNDATION READINESS 265-00-PK-02
AFC drawings
Equipment is on Customs warehouse

Слайд 25

PMC SERVICES FOR BGPP
STATUS OF P1 EQUIPMENT VS FOUNDATION READINESS

215-01-PA-03 A/B, AFC

PMC SERVICES FOR BGPP STATUS OF P1 EQUIPMENT VS FOUNDATION READINESS 215-01-PA-03
drawings available, The works to be performed as per priority based on the backfill mark.

215-02-PA-03 A/B, AFC drawings available, The works to be performed as per priority based on the backfill mark.

Sulfur condenser (all), no data location, foundation, awaiting for AFC drawings

266-00-PK-01 awaiting for AFC drawings
PK-00-5004 no data location, foundation, awaiting for AFC drawings

Awaiting for AFC drawings :
- Sulfur Transfer Pump
- Undegassed Sulfur Pump
- Fuel gas skid

Further slippage of procurement delivery is observed:
Quench Water Pump 215-00-PA-05 A/B
Sulfur Transfer Pump 215-01-PA-04 A/B;215-02-PA-04 A/B
Fuel gas skid: 215-01;215-02
Incinerator Chamber package: 215-01-VA-09; 215-02-VA-09
Waste Heat Boiler, Steam Superheater 215-01-HA-09
Earlier arrival vs. previous week;
Incinerator Combustion Air Blower: 215-01-KB-02 A/B; 215-02-KB-02 A/B

Слайд 26


PMC SERVICES FOR BGPP
CONSTRUCTION- HIGHLIGHTS

Items 5,12,15 were closed for reporting period.
PMC underlines

PMC SERVICES FOR BGPP CONSTRUCTION- HIGHLIGHTS Items 5,12,15 were closed for reporting
that document provision should be improved between Engineering, DCC and Site Construction team.
Focus for AFC drawings issuance is to be prioritized for above items in order to close the Observations as reported by PMC team on daily basis

Слайд 27

REPORTED WEEK 84/129

PMC SERVICES FOR BGPP
CONSTRUCTION- HIGHLIGHTS

There are works ongoing without latest

REPORTED WEEK 84/129 PMC SERVICES FOR BGPP CONSTRUCTION- HIGHLIGHTS There are works
AFC drawings, however it is measured for reporting by EPC Contractor
PMC reflects the progress based on latest AFC drawing only.
AFC drawings issuance is to be prioritized for above items in order to accept the installed quantities.
PMC will report extra quantities in daily report for information purpose, however it will not be counted in actual progress as agreed on 19/08 on the meeting with Client

Слайд 28

REPORTED WEEK 84/129

PMC SERVICES FOR BGPP
CONSTRUCTION- WELDING WORKS

No welding on cooling water

REPORTED WEEK 84/129 PMC SERVICES FOR BGPP CONSTRUCTION- WELDING WORKS No welding
system is recorded during reported week

Слайд 29

REPORTED WEEK 82/127

PMC SERVICES FOR GPP
CONSTRUCTION- HIGHLIGHTS

511-00 Main control room
Reinforcement of

REPORTED WEEK 82/127 PMC SERVICES FOR GPP CONSTRUCTION- HIGHLIGHTS 511-00 Main control
wall columns

511-01 RIB utilities area /512-01
Main substation Reinforcement of foundation

514-01 Mechanical and repair shop
Installation of formwork on flooring monolithic areas

513-01 Gas engine generators building
Concrete curing of foundation

Actual – is a Number of Listed Staff
Actual Overall is increased vs previous week from 577 to 651. Mainly for Labor

Equipment Plan and Actual are for overall project
Actual overall is decreased vs previous week from 195 to 150

Слайд 30

PMC SERVICES FOR BGPP
AREAS OF CONCERN

Pre-commissioning procedures were commented by PMC. Commissioning

PMC SERVICES FOR BGPP AREAS OF CONCERN Pre-commissioning procedures were commented by
Procedures and Execution Plan to be reviewed and commented.
Involve Commissioning specialists as early as possible
Increase Vendor involvements in commissioning
Employ commissioning Sub-contractors

Слайд 31

513-09 Shelter for packaged equipment
Inspection of the horizontal position of lean concrete

513-09 Shelter for packaged equipment Inspection of the horizontal position of lean
formwork

Shooting angle 1 as of 16.08.22

216-01-FA-01 Regeneration Gas Heater
Bolts tightening

Shooting angle 3 as of 16.08.22

PMC SERVICES FOR BGPP
SITE PHOTOS

241-00-PR-01V Pipe rack. Arrangement of gravel-sand mixture base with layer-by-layer compaction

Unit 000. Cooling water interconnecting: 000-WRС-00009-1С3U-4”-HH, 000-WСС-00012-1С3U-4”-HH Pipe welding (Ø219х7mm)