Слайд 2Factory Layout – IRE 1 + IRE 2
Free space for future Cold
Factory Layout – IRE 1 + IRE 2
Free space for future Cold

Rolling process
Free space for future Roller press(Part 2)
Free space for future Roller Heat treatment(Part 2)
Free space for future Roller Grinding channel (Part 2)
New building(Part 1)
Old Building
New building(Part 2) IRE 2
Forklift lanes
Walkways
Слайд 3 No conflict with future plans
REF
shop
Extension for
2nd channel
And roller ch.
move
Step 1
Step
No conflict with future plans
REF
shop
Extension for
2nd channel
And roller ch.
move
Step 1
Step

2
Free
space
All valuable elements of Step1
(foundation, walls etc) will give value
during Step 2, only minor waste.
Слайд 4Tver New Refurbish Process
- Future investments (not included in this IRE)
Total area
Tver New Refurbish Process
- Future investments (not included in this IRE)
Total area

– 720 sq.m
Dirty room
To Factory
Trucks
Future assembly