Winnunga Nimmityjah community health care facility 3d construction staging diagrams seperable portion 1 – piling & underpinning
Содержание
- 2. Excavation Loading From Within Site Bulk Excavation from West to East Shared Driveway Under Traffic Control
- 3. Concrete Pumping From Within Site Basement Slab on Grade – Pour 1 Basement Slab on Grade
- 4. Concrete Pumping From Within Site Ground Floor – Pour 1 Mobile Crane Use From Within Site
- 5. Level 1 – Zone 1 Mobile Crane Use From Within Site Level 1 – Zone 2
- 6. Level 2 – Zone 1 Mobile Crane Use From Within Site Level 2 – Zone 2
- 8. Roof – Zone 1 Mobile Crane Use From Within Site Roof– Zone 2 Scaffold Around Perimeter
- 9. Level 1 – Zone 1 Substation Kiosk Delivery & Commissioning Level 1 – Zone 2 Awning
- 10. Carpark Construction Awning Construction Carpark Construction Scaffold Around Perimeter Shared Driveway Under Traffic Control WINNUNGA NIMMITYJAH
- 11. Shared Driveway Under Traffic Control Carpark Construction Awning Construction Carpark Construction Scaffold Removal Site Accommodation Zone
- 12. Shared Driveway Under Traffic Control Carpark Construction Internal Courtyard Reconfiguration Carpark Construction Landscaping Works WINNUNGA NIMMITYJAH
- 13. Stas – This needs to Be Grass WINNUNGA NIMMITYJAH COMMUNITY HEALTH CARE FACILITY 3D CONSTRUCTION STAGING